Engineer's Estimate and Schedule of Prices

Engineer’s Estimate reports and Scheduled of Prices documents can be created for an individual project item list, as well as for all items in the contract (which includes all projects in the contract).

Engineer’s Estimate (report)

  1. From the contract listing, click on ‘Details’ next to a contract.

  2. Navigate to the Reports section in the Contract Menu, then select Engineer’s Estimate.

  3. Each project will be listed separately; click on the project header to show details.

  4. Either print from the website or click on the ‘3 dots’ at right, click on Exports tab, then ‘Export to CSV’

 

Engineer’s Estimate (document)

  1. From the contract listing, click on ‘Details’ next to a contract.

  2. From the ‘Contract Documents' section, click on the Engineer’s Estimate document template

  3. Create the document from the template

 

Schedule of Prices by Project

  1. From the contract listing, click on ‘Details’ next to a contract.

  2. From the ‘Contract & Project Details' section, click on ‘Details’ next to the specific project.

  3. Click on the Schedule of Prices document template

  4. Create the document from the template

 

Schedule of Prices by Contract

  1. From the contract listing, click on ‘Details’ next to a contract.

  2. From the ‘Contract Documents' section, click on the Schedule of Prices document template

  3. Create the document from the template